[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141357":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141357,799,2,"多选题","某工程双代号时标网络计划，在第5天末进行检查得到的实际进度前锋线如下图所示，正确的是（ ）。2014",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","H工作还剩1天机动时间",false,{"key":16,"text":17,"correct":14},"B","总工期缩短1天",{"key":19,"text":20,"correct":14},"C","H工作影响总工期1天",{"key":22,"text":23,"correct":24},"D","E工作提前1天完成",true,{"key":26,"text":27,"correct":24},"E","G工作进度落后1天","DE","本题考查网络图前锋线与工期。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]