[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141356":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141356,799,2,"多选题","网络进度计划的工期调整可通过（）来实现。2018真题",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","调整关键工作持续时间",true,{"key":16,"text":17,"correct":18},"B","缩短非关键工作的持续时间",false,{"key":20,"text":21,"correct":18},"C","增加非关键工作的时差",{"key":23,"text":24,"correct":14},"D","增减工作项目",{"key":26,"text":27,"correct":14},"E","调整工作间的逻辑关系","ADE","本题考查的是进度计划的调整。网络计划调整的内容包括：（1）调整关键线路的长度。（2）调整非关键工作时差。（3）增减工作项目。（4）调整逻辑关系。（5）重新估计某些工作的持续时间。（6）对资源的投入作相应调整。参见教材47。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]