[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141354":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141354,799,2,"多选题","调整工程网络计划时，调整内容一般包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","非关键工作时差",true,{"key":16,"text":17,"correct":14},"B","关键线路长度",{"key":19,"text":20,"correct":21},"C","工作组织关系",false,{"key":23,"text":24,"correct":21},"D","工作工艺工程",{"key":26,"text":27,"correct":14},"E","工作持续时间","ABE","本题主要考查网络计划调整的内容。 网络计划调整的内容：（1）调整关键线路的长度；（2）调整非关键工作时差；（3） 增、减工作项目；（4）调整逻辑关系；（5）重新估计某些工作的持续时间；（6）对资源的投入作相应调整。 ABE项分别对应（2）（1）（5），故正确。 综上所述，本题正确答案为ABE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]