[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141352":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141352,799,2,"多选题","非关键工作时差可采用的调整方法有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","延长工作的持续时间",true,{"key":16,"text":17,"correct":14},"B","将工作在其最早开始时间与最迟完成时间范围内移动",{"key":19,"text":20,"correct":14},"C","缩短工作的持续时间",{"key":22,"text":23,"correct":24},"D","选择资源强度小或费用低的工作缩短其持续时间",false,{"key":26,"text":27,"correct":24},"E","选择资源占用量大的工作延长其持续时间","ABC","本题主要考查时差的概念。 非关键工作时差可采用的调整方法包括： （1）将工作在其最早开始时间与最迟完成时间范围内移动； （2）延长工作的持续时间； （3）缩短工作的持续时间。 综上所述，本题正确答案为ABC。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]