[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141348":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141348,799,2,"多选题","网络计划调整的内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","调整逻辑关系",true,{"key":16,"text":17,"correct":14},"B","重新估计某些工作的持续时间",{"key":19,"text":20,"correct":21},"C","调整关键工作时差",false,{"key":23,"text":24,"correct":14},"D","调整关键线路的长度",{"key":26,"text":27,"correct":14},"E","增、减工作项目","ABDE","本题主要考查网络计划调整。 ABDE项：网络计划调整的内容包括： （1）调整关键线路的长度； （2）调整非关键工作时差； （3）增、减工作项目； （4）调整逻辑关系； （5）重新估计某些工作的持续时间； （6）对资源的投入作相应调整。 C项：网络计划调整的内容包括调整非关键工作时差，不是关键工作时差。所以C项错误。 综上所述，本题正确答案为ABDE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]