[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141347":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141347,799,1,"单选题","当关键线路的实际进度比计划进度拖后时，应在尚未完成的关键工作中，选择（ ）的工作缩短其持续时间，并重新计算未完成部分的时间参数，将其作为一个新计划实施。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","资源强度小或费用低",true,{"key":16,"text":17,"correct":18},"B","直接费用高",false,{"key":20,"text":21,"correct":18},"C","资源占用量大",{"key":23,"text":24,"correct":18},"D","工作时间长","本题考核的是进度的调整方法。 当关键线路的实际进度比计划进度拖后时，应在尚未完成的关键工作中，选择资源强度小或费用低的工作缩短其持续时间，并重新计算未完成部分的时间参数，将其作为一个新计划实施。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]