[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141345":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141345,799,1,"单选题","当工程网络计划中某项工作的实际进度偏差影响到总工期而需要通过缩短某些工作的持续时间调整进度计划时，这些工作是指（ ）的可被压缩的工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","关键线路和超过计划工期的非关键线路上",true,{"key":16,"text":17,"correct":18},"B","关键线路上资源消耗量比较少",false,{"key":20,"text":21,"correct":18},"C","关键线路上持续时间比较长",{"key":23,"text":24,"correct":18},"D","施工工艺及采用技术比较简单","本题主要考查工期调整。 调整工期时，压缩关键路线和超过计划工期的非关键线路上的工作可以缩短工期，压缩计划工期内非关键线路上的工作对总工期没有影响。所以当总工期需要调整时，通过缩短某些关键线路和超过计划工期的非关键线路上工作的持续时间，可以达到缩短工期的目的。 综上所述，本题正确选项为A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]