[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141341":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141341,799,2,"多选题","关于判别网络计划关键线路的说法，正确的有（ ）。 2016",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","相邻两工作间的间隔时间均为零的线路",false,{"key":16,"text":17,"correct":14},"B","双代号网络计划中无虚箭线的线路",{"key":19,"text":20,"correct":21},"C","总持续时间最长的线路",true,{"key":23,"text":24,"correct":14},"D","双代号网络计划中由关键节点组成的线路",{"key":26,"text":27,"correct":21},"E","时标网络计划中无波形线的线路","CE","本题考查的是关键工作、关键线路和时差的确定。选项A，从起点节点开始到终点节点均为关键工作，且所有工作的时间间隔均为零的线路应为关键线路。选项B，关键线路上是可以有虚工作的，虚工作不占用时间和资源；选项D，关键节点组成的线路不一定是关键线路，而关键线路上的节点必定是关键节点。参见教材50。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]