[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141335":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141335,799,2,"多选题","某分部工程双代号网络计划如下图所示，提供的正确信息有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工作B为关键工作",false,{"key":16,"text":17,"correct":14},"B","工作D的自由时差为4",{"key":19,"text":20,"correct":21},"C","工作F为关键工作",true,{"key":23,"text":24,"correct":14},"D","工作E为非关键工作",{"key":26,"text":27,"correct":21},"E","工作M、H为非关键工作","CE","本题主要考查时差计算。 ACDE项：节点的时间参数分别是最早开始和最迟开始时间，最早开始时间等于最迟开始时间的节点是关键节点，可以得出关键线路是F - E - G - N，工作FEGN都是关键工作，故CE项正确，AD项错误。 B项：D工作的最迟完工时间是4，最早完工时间是2，所以D工作自由时差为2。因此B项错误。 综上所述，本题正确答案为CE。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]