[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141332":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141332,799,2,"多选题","在工程网络计划中，当计划工期等于计算工期时，关键工作的判定（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","该工作的总时差为零",true,{"key":16,"text":17,"correct":18},"B","该工作与其紧后工作之间的时间间隔为零",false,{"key":20,"text":21,"correct":14},"C","该工作的最早开始时间与最迟开始时间相等",{"key":23,"text":24,"correct":18},"D","该工作的自由时差最小",{"key":26,"text":27,"correct":18},"E","该工作的持续时间最长","AC","本题考核的是关键工作的内容。 关键工作是总时差为最小的工作。当计划工期等于计算工期时，工作的总时差为零是最小的总时差，此工作是关键工作。总时差可以用工作的最迟开始时间减去最早开始时间或用工作的最迟完成时间减去最早完成时间。 综上所述，正确选项为AC。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]