[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141327":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141327,799,1,"单选题","某工程双代号网络计划如下图所示，其关键线路有（ ）条。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","2",{"key":19,"text":20,"correct":21},"C","3",true,{"key":23,"text":24,"correct":14},"D","4","本题考核的是双代号网络计划。 总时间最长的是关键线路。箭线下方的数字表示该工作的时间，从图中可以看出，关键线路有3条，分别为1-3-4-7-10-12，1-2-6-9-11-12，1-3-4-6-9-11-12 ，总时间均为35。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]