[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141326":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141326,799,1,"单选题","某工程双代号网络计划如下图所示，其关键线路有（ ）条。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","本题主要考查关键线路。 关键线路是工作持续时间最长的线路。可以通过计算路线工作时间得到。 本题中共有9条线路，对应的工作持续时间分别为： 所以关键线路是工作时间为18天的两条线路。 综上所述，本题正确选项是B项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]