[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141323":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141323,799,1,"单选题","在双代号网络计划中，关键工作是指（ ）的工作。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","最迟完成时间与最早完成时间之差最小",true,{"key":16,"text":17,"correct":18},"B","持续时间最长",false,{"key":20,"text":21,"correct":18},"C","两端节点均为关键节点",{"key":23,"text":24,"correct":18},"D","自由时差最小","本题主要考查关键工作的概念。 在双代号网络计划中，总时差最小的工作是关键工作。总时差=最迟开工时间－最早开工时间=最迟完工时间－最早完工时间。因此，最迟完成时间与最早完成时间之差最小的工作为关键工作。 综上所述，本题正确答案为A。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]