[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141319":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141319,799,1,"单选题","某分部工程单代号网络计划如下图所示，节点中下方的数字为该工作的持续时间，单位：天。其关键线路有（ ）条。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","本题考核的是关键线路。 关键线路为总工期最长的路线。总工期为48天，用标号法计算得出共有2条路线：A-B-D-G-H-J-F和A-C-G-H-J-F。 综上所述，正确选项为B。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]