[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141318":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141318,799,1,"单选题","下图所示双代号网络计划的关键路线为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","①-⑧",false,{"key":16,"text":17,"correct":14},"B","①-②-⑥-⑧",{"key":19,"text":20,"correct":14},"C","①-③-⑦-⑧",{"key":22,"text":23,"correct":24},"D","①-④-⑤-⑦-⑧",true,"本题主要考查对双代号网络计划中的关键线路的理解。 双代号网络计划中，总的工作持续时间最长的线路为关键线路。四个选项的持续时间分别为9、10、13、14天，故D项正确。 综上所述，本题正确答案为D。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]