[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141317":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141317,799,2,"多选题","（2020年真题）某双代号网络计划如下图，关于工作时间参数的说法，正确的有（ ）",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作B的最迟完成时间是第8天",true,{"key":16,"text":17,"correct":18},"B","工作C的最迟开始时间是第7天",false,{"key":20,"text":21,"correct":18},"C","工作F的自由时差是1天",{"key":23,"text":24,"correct":14},"D","工作G的总时差是2天",{"key":26,"text":27,"correct":18},"E","工作H的最早开始时间是第13天","AD","P130-142 工作B的最迟完成时间=15-7=8。 工作C的最迟开始时间=15-2-4-3=6。 工作F的自由时差=（2+4+6）-（2+4+4）=2。 工作G的总时差=15-7-(2+4)=2。 工作H的最早开始时间=2+4+6=12。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]