[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141312":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141312,799,1,"单选题","（2019年真题）某工程网络计划图如下，工作D的最迟开始时间是第（）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","5",{"key":19,"text":20,"correct":14},"C","6",{"key":22,"text":23,"correct":24},"D","8",true,"P130-142 本题考查的是双代号网络计划的参数计算(按节点计算法)。由可知工作D的最迟完成时间是12，持续时间是4,所以工作D的最迟开始开始时间是12-4=8天。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]