[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141311":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141311,799,1,"单选题","某工作有三项紧后工作，持续时间分为4天、5天、6天，对应的最迟完成时间分别为第18天、第16天、第14天，则该工作的最迟完成时间是第（）天。2018真题",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","14",false,{"key":16,"text":17,"correct":14},"B","12",{"key":19,"text":20,"correct":21},"C","8",true,{"key":23,"text":24,"correct":14},"D","6","本题考查的是双代号网络计划时间参数的计算。由题可知，三项紧后工作的最迟开始时间分别为14天、11天、8天，一项工作的最迟完成时间等于各紧后工作的最迟开始时间的最小值，所以选择8天。参见教材33。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]