[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141309":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141309,799,2,"多选题","某工程双代号网络计划如下图，已标出各项工作的最早开始时间（ESi-j）、最迟开始时间（LSi-j）和持续时间（Di-j）。2018真题该网络计划表明（）。2018真题",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作C和工作E均为关键工作",false,{"key":16,"text":17,"correct":18},"B","工作B的总时差和自由时差相等",true,{"key":20,"text":21,"correct":18},"C","工作D的总时差和自由时差相等",{"key":23,"text":24,"correct":18},"D","工作G的总时差、自由时差分别为2天和0天",{"key":26,"text":27,"correct":18},"E","工作J的总时差和自由时差相等","BCDE","本题考查的是双代号网络计划时间参数的计算。选项C，工作C不是关键工作。参见教材34。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]