[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141308":3},{"question":4,"library":23},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":22},1141308,799,1,"单选题","某双代号网络计划如下图（单位：天），则工作E的自由时差为（）天。2018真题",[11,15,19],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","4","本题考查的是双代号网络计划时间参数的计算。本工作自由时差=紧后工作的最早开始时间的最大值-本工作的最早完成时间=H工作的最早开始时间-E工作的最早完成时间=20-18=2（天）。参见教材33。",{"id":6,"name":24,"category":25,"favorite":26},"一建建设工程项目管理","建筑工程",0]