[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141306":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141306,799,1,"单选题","某单代号网络计划如下图，工作 A、D之间的时间间隔是（ ）天。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","0",false,{"key":16,"text":17,"correct":14},"B","1",{"key":19,"text":20,"correct":21},"C","2",true,{"key":23,"text":24,"correct":14},"D","3","本题考查的是单代号网络计划时间参数的计算。相邻两项工作之间的时间间隔等于紧后工作的最早开始时间和本工作的最早完成时间之差。工作A的最早完成时间为4，工作D的最早开始时间为6，6-4=2，故工作A、D之间的时间间隔为2天。参见教材42。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]