[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141305":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141305,799,1,"单选题","某工程双代号网络计划如下图，其计算工期是（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","11",false,{"key":16,"text":17,"correct":14},"B","13",{"key":19,"text":20,"correct":14},"C","15",{"key":22,"text":23,"correct":24},"D","22",true,"本题考查的是双代号网络计划时间参数的计算。其关键线路为①→③→④→⑤→⑥→⑧，工期为7+9+6=22天。参见教材37。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]