[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141304":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141304,799,1,"单选题","某工作有且仅有两个紧后工作 C、 D，其中C工作最早开始时间为10（计算坐标系,下同），最迟完成时间为18，持续时间为5天；D工作最早完成时间为18，最迟完成时间为20，持续时间为6天；该工作与C工作间的时间间隔为2天，与D工作间的时间间隔为4天，则该工作的总时差为（ ）天。2014",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","3",false,{"key":16,"text":17,"correct":14},"B","4",{"key":19,"text":20,"correct":21},"C","5",true,{"key":23,"text":24,"correct":14},"D","6","本题考查的是双代号网络计划时间参数的计算。参见教材40。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]