[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141300":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141300,799,1,"单选题","某双代号网络计划中。工作M的最早开始时间和最迟开始时间分别为第12天和第15天，其持续时间为5天。工作M有3项紧后工作，它们的最早开始时间分别为第21天、第24天和第28天，则工作M的自由时差为（ ）天。 2016",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":21},"C","4",true,{"key":23,"text":24,"correct":14},"D","5","本题考查的是双代号网络计划时间参数的计算。自由时差，是指在不影响其紧后工作最早开始的前提下，可以利用的机动时间。M的最早完成时间为12+5=17天，而其紧后工作中的最早开始时间为21天，所以M的自由时差为21-17=4天。参见教材38。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]