[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141298":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141298,799,1,"单选题","某双代号网络计划中，工作A有两项紧后工作B和 C，工作B和工作C的最早开始时间分别为第13天和第15天，最迟开始时间分别为第19天和第21天；工作A与工作B和工作C的间隔时间分别为0天和2天。如果工作A实际进度拖延7天，则（ ）。 2016",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","对工期没有影响",false,{"key":16,"text":17,"correct":14},"B","总工期延长2天",{"key":19,"text":20,"correct":14},"C","总工期延长3天",{"key":22,"text":23,"correct":24},"D","总工期延长1天",true,"本题考查的是双代号网络计划时间参数的计算。A工作有两项紧后工作，A-B线路的总时差为19-13=6天，A-C线路的总时差为21-15+2=7天，二者取最小值，那么A工作的总时差为6天，如果A的实际进度延误7天，影响总工期1天。参见教材37。@jin",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]