[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141295":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141295,799,1,"单选题","某双代号时标网络计划如下图，如 B、 D、I工作共用同一台施工机械且按B-D-I顺序施工，则对网络计划可能造成的影响是（ ）。 2016",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","总工期不会延长，但施工机械会在现场闲置1周",false,{"key":16,"text":17,"correct":14},"B","总工期会延长1周，但施工机械在现场不会闲置",{"key":19,"text":20,"correct":21},"C","总工期不会延长，且施工机械在现场不会闲置",true,{"key":23,"text":24,"correct":14},"D","总工期会延长1周，且施工机械会在现场闲置1周","本题考查的是双代号时标网络计划。BDI三个工作，按照顺序施工，那么B工作是第4周完成，D工作需要第5周开始，致使D工作拖延1周，但是H工作有1周自由时差，那么ADH线路不影响总工期。D工作第10周结束，I工作第11周开始，持续4个月，到第14个月正好完成，所以BEI线路不影响总工期。@jin",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]