[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141292":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141292,799,1,"单选题","某工作的最早开始时间是5，最早结束时间9，最迟开始时间7，则该工作的最迟完成时间是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","11",true,{"key":16,"text":17,"correct":18},"B","12",false,{"key":20,"text":21,"correct":18},"C","13",{"key":23,"text":24,"correct":18},"D","14","本题主要考查双代号网络计划时间参数的计算。 总时差是指在不影响总工期的前提下，某工作可利用的机动时间。 计算公式为：总时差=最迟完工时间-最迟开工时间=最早完工时间-最早开工时间 本题中，总时差=最早完工时间-最早开工时间=9-5=4天，所以，最迟完工时间=总时差+最迟开工时间=4+7=11 综上所述，本题正确答案为A。@jin",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]