[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141286":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141286,799,1,"单选题","单代号网络计划的自由时差等于（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","该工作与紧前工作时间间隔的最大值",false,{"key":16,"text":17,"correct":14},"B","该工作与紧后工作时间间隔的最大值",{"key":19,"text":20,"correct":14},"C","该工作与紧前工作时间间隔的最小值",{"key":22,"text":23,"correct":24},"D","该工作与紧后工作时间间隔的最小值",true,"本题主要考查单代号网络计划时间参数的计算。 单代号网络计划自由时差：若工作i无紧后工作，其自由时差等于计划工期减去该工作的最早完成时间；若工作i有紧后工作j时，其自由时差等于该工作与其紧后工作j之间的时间间隔的最小值。 综上所述，本题正确选项为D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]