[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141279":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141279,799,1,"单选题","某双代号网络计划中（以天为单位），工作K的最早开始时间为6，工作持续时间为4，工作M的最迟完成时间为22。工作持续时间为10，工作N的最迟完成时间为20，工作持续时间为5，已知工作K只有M，N两项紧后工作，工作K的总时差为（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","2",true,{"key":16,"text":17,"correct":18},"B","3",false,{"key":20,"text":21,"correct":18},"C","5",{"key":23,"text":24,"correct":18},"D","6","",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]