[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141276":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141276,799,1,"单选题","工期泛指完成任务所需要的时间，在其类型中，（ ）用TC表示。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","计算工期",true,{"key":16,"text":17,"correct":18},"B","要求工期",false,{"key":20,"text":21,"correct":18},"C","总工期",{"key":23,"text":24,"correct":18},"D","计划工期","本题主要考查工期的表示。 工期有三种表示方式： （1）计算工期，根据网络计划时间参数计算出来的工期，用TC表示； （2）要求工期，任务委托人所要求的工期，Tr表示； （3）计划工期，根据要求工期和计算工期所确定的作为实施目标的工期，Tp表示。 综上所述，本题正确选项是A项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]