[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141272":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141272,799,1,"单选题","某工程网络计划中工作B的持续时间为5天，其两项紧前工作的最早完成时间分别为第6天和第8天，则工作B的最早完成时间为第（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","6",false,{"key":16,"text":17,"correct":14},"B","8",{"key":19,"text":20,"correct":14},"C","11",{"key":22,"text":23,"correct":24},"D","13",true,"本题主要考查工期计算。 最早完成时间EFi-j是指在各紧前工作全部完成后，工作i-j完成的最早时刻，EFA=8+5=13天。 综上所述，本题正确选项是D项。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]