[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141268":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141268,799,1,"单选题","已知工程网络计划中某工作的自由时差为5d，总时差为7d。监理工程师在检查进度时发现只有该工作实际进度拖延，且影响工期3d，则该工作实际进度比计划进度拖延（ ）d。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","10",true,{"key":16,"text":17,"correct":18},"B","8",false,{"key":20,"text":21,"correct":18},"C","7",{"key":23,"text":24,"correct":18},"D","3","本题主要考查总时差和自由时差对工期的影响。 总时差是指在不影响总工期的前提下，该工作可以利用的机动时间；自由时差是指在不影响紧后工作最早开工时间的前提下，该工作可以利用的机动时间。该工作影响总工期3d，所以该工作拖延时间超过总时差3d，该工作实际进度比计划进度拖延10d。 综上所述，本题正确选项为A项",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]