[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141265":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141265,799,1,"单选题","单代号网络图中工作的最早完成时间等于（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","该工作的各个紧前工作的最早完成时间的最大值",false,{"key":16,"text":17,"correct":14},"B","该工作的各个紧前工作的最早完成时间的最小值",{"key":19,"text":20,"correct":21},"C","该工作的最早开始时间加该工作的持续时间",true,{"key":23,"text":24,"correct":14},"D","该工作的最迟开始时间减该工作的自由时差","本题主要考查对单代号网络图的理解。 工作最早完成时间等于该工作最早开始时间加上其持续时间。 综上所述，本题正确答案为C。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]