[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141262":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141262,799,2,"多选题","（2020年真题）下列双代号网络图中，存在的绘图错误有（ ）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","存在多个起点节点",true,{"key":16,"text":17,"correct":14},"B","箭线交叉的方式错误",{"key":19,"text":20,"correct":21},"C","存在相同节点编号的工作",false,{"key":23,"text":24,"correct":21},"D","存在没有箭尾节点的箭线",{"key":26,"text":27,"correct":14},"E","存在多余的虚工作","ABE","P118-129 A选项，有①②两个起点节点。 B选项，应采用过桥法或者指向法。 E选项，②③之间虚工作没有必要。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]