[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141260":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141260,799,1,"单选题","（2020年真题）各工作间逻辑关系表及相应双代号网图如下图。图中虛箭线的作用是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","联系",false,{"key":16,"text":17,"correct":18},"B","区分",true,{"key":20,"text":21,"correct":14},"C","断路",{"key":23,"text":24,"correct":14},"D","指向","P118-129 虚箭线是实际工作中并不存在的一项虚设工作，故它们既不占用时间，也不消耗资源，一般起着工作之间的联系、区分和断路三个作用。联系作用是指应用虚箭线正确表达工作之间相互依存的关系。题目中主要的作用是区分。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]