[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141259":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141259,799,1,"单选题","（2020年真题）某双代号网络计划如下图，关键线路有（ ）条。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","3",true,{"key":16,"text":17,"correct":18},"B","1",false,{"key":20,"text":21,"correct":18},"C","2",{"key":23,"text":24,"correct":18},"D","4","P118-129 在各条线路中，有一条或几条线路的总时间最长，称为关键线路，一般用双线或粗线标注。 本题中分别为：A-E-I-L，C-E-I-L，C-G-J-M这三条线路。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]