[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141258":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141258,799,1,"单选题","关于虚工作的说法，正确的是（ ）。( 2015真题 )",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","虚工作只在双代号网络计划中存在",false,{"key":16,"text":17,"correct":14},"B","虚工作一般不消耗资源但占用时间",{"key":19,"text":20,"correct":21},"C","虚工作可以正确表达工作间逻辑关系",true,{"key":23,"text":24,"correct":14},"D","双代号时标网络计划中虚工作用波形表示","本题考查的是双代号网络计划。在双代号网络图中，为了正确地表达图中工作之间的逻辑关系，往往需要应用虚箭线。虚箭线是实际工作中不存在的一项虚工作，故它们既不占用时间，也不消耗资源，一般起着工作之间的联系、区分和断路三个作用。双代号时标网络计划中应以实箭线表示工作，以虚箭线表示虚工作。所以，选项C是正确的。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]