[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141254":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141254,799,2,"多选题","某单代号网络图如下图所示，存在的错误有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","多个起点节点",true,{"key":16,"text":17,"correct":14},"B","有多余虚箭线",{"key":19,"text":20,"correct":21},"C","出现交叉箭线",false,{"key":23,"text":24,"correct":21},"D","没有终点节点",{"key":26,"text":27,"correct":21},"E","出现循环回路","AB","本题考查单代号网络计划图的特点：工作之间的逻辑关系容易表达，且不用虚箭线，故绘图较简单；网络图便于检查和修改；由于工作持续时间表示在节点之中，没有长度，故不够直观；表示工作之间逻辑关系的箭线可能产生较多的纵横交叉现象。参见教材35。@##",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]