[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141253":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1141253,799,1,"单选题","图示的双代号网络图中H工作有（ ）个先行工作。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":14},"B","3",{"key":19,"text":20,"correct":14},"C","4",{"key":22,"text":23,"correct":24},"D","6",true,"本题主要考查对双代号网络图的理解。 自起点节点开始至某工作之前的同一条线路上的所有工作叫做该工作的先行工作。即某工作之前需要先行完成的所有工作。本题中，H工作的紧前工作包括C、E、G，这三者的紧前工作包括A、B、D，起点节点为A，故有6个先前工作。 综上所述，本题正确答案为D。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]