[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141250":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141250,799,1,"单选题","某工作间逻辑关系如下图，则正确的是（ ）。2017",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","A、B均完成后同时进行 C、D",false,{"key":16,"text":17,"correct":18},"B","A、B均完成后进行DE",true,{"key":20,"text":21,"correct":14},"C","C均完成后同时进行",{"key":23,"text":24,"correct":14},"D","C完成后进行E","本题考查双代号网络计划中的各种工作的逻辑关系。A选项中，A、B工作均完成后进行D工作，C工作与AB工作没有先后逻辑关系。A选项错误。ABC工作均完成后，E工作才能开始，D选项错误。@##",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]