[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141249":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141249,799,1,"单选题","双代号网络计划如下图，其关键线路有（）条。2018真题",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":18},"B","3",true,{"key":20,"text":21,"correct":14},"C","2",{"key":23,"text":24,"correct":14},"D","1","本题考查的是双代号网络计划。关键线路为：A→D→H→K，A→E→I→K和A→G→I→K，共3条。参见教材23。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]