[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141248":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141248,799,2,"多选题","某双代号网络计划如下图，绘图的错误有（）。2018真题",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","有多个终点节点",false,{"key":16,"text":17,"correct":18},"B","有多个起点节点",true,{"key":20,"text":21,"correct":14},"C","存在循环回路",{"key":23,"text":24,"correct":18},"D","有多余虚工作",{"key":26,"text":27,"correct":18},"E","节点编号有误","BDE","本题考查的是双代号网络计划。选项B，有①和②两个起点节点。选项D，有多余虚工作②→③和②→④。选项E，有两个节点⑨。参见教材23～124。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]