[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141247":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141247,799,1,"单选题","某双代号时标网络计划如下图，工作 F、工作H的最迟完成时间分别为（）。2018真题",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","第8天、第11天",false,{"key":16,"text":17,"correct":14},"B","第8天、第9天",{"key":19,"text":20,"correct":21},"C","第7天、第11天",true,{"key":23,"text":24,"correct":14},"D","第7天、第9天","本题考查的是双代号时标网络计划。识图发现，工作F的最早完成时间为第5天，工作F的总时差为2天，所以工作F的最迟完成时间=5+2=7（天）。工作H的最早完成时间为第9天，工作H的总时差为2天，所以工作H的最迟完成时间=9+2=11（天）。所以选项C正确。参见教材25。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]