[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141246":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1141246,799,1,"单选题","某双代号网络图如下图所示，正确的是（ ）。2014",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工作 C、D 应同时完成",false,{"key":16,"text":17,"correct":14},"B","工作B的紧后工作只有工作D",{"key":19,"text":20,"correct":21},"C","D完成后即可进行工作G",true,{"key":23,"text":24,"correct":14},"D","工作D完成后即可进行工作F","本题考查的是双代号网络计划。选项A：C、D不一定同时完成；选项B：工作B的紧后工作有工作C、D、E；选项D：工作C完成后即可进行工作F。参见教材30。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]