[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141245":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141245,799,2,"多选题","某双代号网络计划如下图（图中粗实线为关键工作），若计划工期等于计算工期，则自由时差一定等于总时差且不为零的工作有（ ）。2017",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","①－②",true,{"key":16,"text":17,"correct":18},"B","③－⑤",false,{"key":20,"text":21,"correct":18},"C","②－⑦",{"key":23,"text":24,"correct":14},"D","④－⑤",{"key":26,"text":27,"correct":14},"E","⑥－⑧","ADE","本题考查的是双代号网络计划。当计划工期等于计算工期时，只要完成节点是关键节点，那么这项工作的自由时差和总时差是相等的，且不一定为零。参见教材27。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]