[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141244":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141244,799,2,"多选题","某工程工作逻辑关系如下表，C工作的紧后工作有（ ）。2017",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工作H",true,{"key":16,"text":17,"correct":18},"B","工作G",false,{"key":20,"text":21,"correct":14},"C","工作F",{"key":23,"text":24,"correct":14},"D","工作E",{"key":26,"text":27,"correct":18},"E","工作D","ACD","本题考查的是双代号网络计划。在表格中，C作为E、F、H的紧前工作，那么C工作的紧后工作就是E、F、H。参见教材29。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]