[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141242":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1141242,799,1,"单选题","某双代号时标网络计划如下图，工作G的最迟开始时间是第（ ）天。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","4",false,{"key":16,"text":17,"correct":18},"B","5",true,{"key":20,"text":21,"correct":14},"C","6",{"key":23,"text":24,"correct":14},"D","7","本题考查的是双代号时标网络计划。从该图中可以判断出G工作的最早开始时间是4天，总时差是1天，那么总时差=最迟开始时间-最早开始时间，可以求出最迟开始时间为4+1=5天。参见教材30。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]