[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141241":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141241,799,1,"单选题","根据《工程网络计划技术规程》JQJ\u002FT121-2015，网络图存在的绘图错误是（ ）。2017",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","编号相同的工作",true,{"key":16,"text":17,"correct":18},"B","多个起点节点",false,{"key":20,"text":21,"correct":18},"C","相同的节点编号",{"key":23,"text":24,"correct":18},"D","无箭尾节点的箭线","本题考查的是工程网络计划的编制方法。①→②有两个工作，所以有编号相同的两个工作。参见教材27。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]