[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141239":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1141239,799,1,"单选题","某双代号网络计划中，工作M的自由时差3天，总时差5天。在进度计划实施检查中发现工作M实际进度落后，且影响总工期2天。在其他工作均正常的前提下，工作M的实际进度落后（ ）天。 2016",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","7",true,{"key":16,"text":17,"correct":18},"B","5",false,{"key":20,"text":21,"correct":18},"C","6",{"key":23,"text":24,"correct":18},"D","8","本题考查的是双代号网络计划。因为本项工作已有总时差5天，但还是影响总工期2天，所以工作M的实际进度是落后了5+2=7天。参见教材27。",{"id":6,"name":27,"category":28,"favorite":29},"一建建设工程项目管理","建筑工程",0]