[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1141238":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1141238,799,2,"多选题","某工程项目的双代号时标网络计划，当计划执行到第4周末及第10周末时，检查得出实际进度前锋线如下图所示，检查结果表明（ ）。( 2015真题 )",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","第4周末检查时工作B拖后1周，但不影响总工期",false,{"key":16,"text":17,"correct":18},"B","第4周末检查时工作A拖后1周，影响总工期1周",true,{"key":20,"text":21,"correct":18},"C","第10周末检查时工作G拖后1周，但不影响总工期",{"key":23,"text":24,"correct":14},"D","第10周末检查时工作I提前1周，可使总工期提前1周",{"key":26,"text":27,"correct":14},"E","在第5周到第10周内，工作F和工作I的实际进度正常","BC","本题考查的是双代号时标网络图。选项A，正确的表述应是“第4周末检查时工作B拖后2周，但影响总工期1周”；选项D，H工作进度正常，受H的制约，K工作不能提前开始，因此不能使总进度提前1周；选项E，正确的表述应是“在第5周到第10周内，工作F和工作I的实际进度超前”。参见教材33。",{"id":6,"name":31,"category":32,"favorite":33},"一建建设工程项目管理","建筑工程",0]